Sample supplier audit report

This is what you receive after an audit. Every audit, by any auditor in any country, produces a report in this structure, with severity assigned by the same written rules.

Report ref.
DQN-A1-ILLUS-01
Service
A1 Supplier Audit
Revision
1.0
Status
Illustrative
Constructed example This report was written for this website. The client, supplier, site and findings are fictional, and the numbers are illustrative. It is not from a client audit. It shows the format and the standard of evidence we hold every report to.

1. Cover and identification

Report reference
DQN-A1-ILLUS-01
Audit type
A1 Supplier Audit
Requirements applied
Client A supplier quality manual, rev. 4; Supplier X control plans, work instructions and procedures for the processes in scope
Client
Client A (fictional)
Audited organisation
Supplier X (fictional): semiconductor assembly and test subcontractor, Penang, Malaysia
Site scope
Die attach, wire bond, moulding and final visual inspection on assembly lines 1 and 2
On site
Two consecutive days, including part of the night shift
Auditor
MY-00 (example code) · Certified Auditor, level L4 · process specialism: wire bond. The auditor’s name appears only on the signed declaration released to the client.
Report issued
Five working days after the last day on site · version 1.0
Distribution
Client A quality and purchasing. Supplier X quality manager receives sections 1–7 and 9. Confidential.

2. Executive summary

0Critical
3Major
4Minor
2Observations

Result: Re-audit required. Supplier X runs a stable, well-documented assembly operation with good incoming material control. One Major finding (F-07) is systemic: it occurred on every shift sampled. Under our classification rules (section 4), a systemic Major means the result can improve only after on-site verification.

Themes across the findings

  • Measurement discipline. A destructive bond test performed less often than the control plan requires (F-07), and a measurement system replaced without being re-validated (F-02).
  • Containment. Rejected units were physically separated but not identified (F-06).
  • Records. Four isolated lapses in document, training, ESD and traceability records (F-01, F-03, F-04, F-05). Each control is otherwise working.

Before the next shipment

Lots bonded during the period covered by F-07 were on hold at the time of audit. Their disposition should be confirmed before release.

Recommendation

Continue current supply under Client A’s normal incoming controls. Don’t release new part numbers to Supplier X until F-07 and F-02 are verified closed at a follow-up visit (service A6). The approval decision is Client A’s.

3. Scope and method

Covered

Die attach, wire bond, moulding and final visual inspection on lines 1 and 2. Day shift observed in full; night shift observed for two hours on wire bond and moulding.

Not covered

Electrical test, packing and shipping, sub-tier supplier management, and the calibration laboratory (records were reviewed instead of a lab visit).

Method

The audit followed the approach of ISO 19011: document review, observation on the floor, record sampling and interviews. Staff are identified in this report by role only.

Sampling
RecordsSampledBasis
Wire bond ball shear records21 of 21 shiftsTwo bonders, seven consecutive production days
Lot travellers12Random, from finished goods in the last 30 days
Operator training records6Operators on shift during the audit
Equipment change records5All changes to control-plan measurement devices in 12 months
ESD wrist strap logs2 lines × 1 weekMost recent full week

Limitations

  • Night shift was observed for two hours only.
  • Photography was not permitted on the production floor. Evidence is recorded as document references and written observations.

4. Result and classification

The result is set by these rules, not by the auditor’s overall impression:

ResultRule
MeetsNo Critical and no Major findings
Meets with conditionsNo Critical; 1–3 Majors, none systemic, each with an agreed action and date
Re-audit requiredNo Critical; 4 or more Majors, or any systemic Major
Does not meetAny Critical finding, or evidence of altered or falsified records

This audit: no Critical, three Majors, one of them systemic (F-07). Result: Re-audit required.

VDA 6.3 process audits use VDA 6.3’s own rating and A, B or C classification instead of this table.

5. Findings register

IDSeverityCategoryRequirementFinding
F-01MinorDOCDocument control procedure: only the current revision at point of useDie attach epoxy thaw instruction at one station was rev. C; rev. D (thaw time changed from 30 to 45 minutes) was released three weeks earlier.
F-02MajorMEASControl plan, loop height: measured by optical system; measurement system analysis after any change to the systemThe loop height microscope was replaced four months ago. No gauge R&R was performed on the replacement.
F-03MinorTRAINTraining procedure: certification renewed every 12 monthsOne of six moulding operators sampled had certification two months past renewal. The operator was observed working correctly.
F-04MinorHANDESD control programme: wrist strap test logged at every shift startTwo shift-start entries missing on line 2 in the week sampled.
F-05MinorTRACETraceability procedure: capillary lot recorded on the lot travellerCapillary lot missing on 1 of 12 travellers sampled.
F-06MajorNC-PRODNonconforming product procedure: every reject container tagged with lot, defect and disposition statusThree reject bins in the material review area had no hold tags. Product was physically separated but not identified.
F-07MajorPROC-CTRLControl plan, ball shear: every 2 hours, 5 bonds per bonderBall shear tested once per shift instead of every 2 hours, on every shift sampled. Full record below.

Full finding record — F-07

Every finding carries these fields. F-07 is shown in full as the example.

F-07 · PROC-CTRLMajor · Systemic
Process area
Wire bond — post-bond destructive monitor (ball shear)
Requirement
Control plan, ball shear line: test every 2 hours, 5 bonds per bonder. Reaction plan: hold all units bonded since the last conforming test.
Finding
Ball shear was tested once per shift instead of every 2 hours, on all three shifts, throughout the sampled period. All recorded results were within limits.
Objective evidence
E-03: ball shear records for two bonders over seven production days, 21 of 21 shifts reviewed. E-04: interview with line technician (role only). E-05: current control plan and reaction plan.
Extent
Systemic — every shift sampled
Risk
If bond strength drifted, up to one full shift of bonded units (about 8 hours) would be suspect, not 2 hours. The test is destructive, so suspect units can’t be screened later in the process.
Containment
Required. Lots from the sampled period were identified and on hold at the time of audit, which is why this is Major and not Critical.
Root cause
To be provided by Supplier X
Corrective action
To be provided by Supplier X
Action owner
Role: wire bond process engineering lead
Response due
Containment 5 working days · root cause and corrective action 15 working days
Verification
On-site, at a follow-up audit (A6), within 60 days
Status
Open

6. Observations and positive practices

Observations are risks, not nonconformities. They are kept separate from the findings so they can’t be mistaken for them.

IDTypeNote
O-1ObservationBonder-to-bonder correlation depends on one senior technician. The method isn’t written down, so it would be at risk if that person left.
O-2ObservationSPC charts for die shear are reviewed weekly. This meets the procedure, but a shift that drifts could run for several days before anyone reviews it.
P-1PositiveIncoming wire lots are checked against the certificate of analysis before release, and mismatches are logged and escalated.
P-2PositiveFinal visual inspection stations have boundary samples for each defect type, and inspectors could explain them.

7. Evidence appendix (extract)

Ref.EvidenceSupports
E-01Work instruction, epoxy thaw, rev. C at station DA-2; document register showing rev. D releasedF-01
E-02Equipment change record for the loop height microscope; MSA register with no entry after the changeF-02
E-03Ball shear records, two bonders, seven production daysF-07
E-04Interview notes, line technician (role only)F-07
E-05Control plan and reaction plan, current revisionF-07
E-06Material review area walk-through notes, three untagged bins listed by locationF-06

8. Auditor declaration

I conducted this audit in line with the scope and method stated in section 3. Each finding rests on the evidence recorded in section 7. I hold the qualifications stated in section 1, and their verification status is on file with Datum Quality Network.

Before accepting this engagement I declared that I have no current or former employment, financial interest or family connection with Supplier X. I will keep everything I saw and was told during this audit confidential.

Signed by the auditor. The signed copy, with the auditor’s name, is released to the client only.

9. Corrective action request

Supplier X is asked to respond to each finding by these deadlines, set by severity:

SeverityContainmentRoot cause and actionClosure verified
Critical24 hours5 working daysWithin 30 days, on site
Major5 working days15 working daysWithin 60 days
Minor—20 working daysWithin 90 days, document review

How a root cause is reviewed — F-02

We review every response before it’s accepted. Here is a first response that was sent back, and the revised one that was accepted.

F-02 · First responseRejected

Supplier’s root cause: “The engineer forgot to request MSA after the microscope was replaced.”

Supplier’s action: “Retrain the engineer.”

Why it was sent back:

  • It blames a person. It doesn’t explain why the change process allowed a measurement device to go into use without MSA.
  • It stops at the first “why”.
  • Retraining one person doesn’t stop the same gap on the next equipment change.
  • It doesn’t say whether other devices were changed the same way.
F-02 · Revised responseAccepted · pending verification

Root cause: The equipment change procedure has no step requiring MSA when a device used to measure a control-plan characteristic is replaced. The change form has no MSA field, so nothing prompts it.

Corrective action:

  • A mandatory MSA step added to the equipment change form for any device listed in a control plan.
  • Gauge R&R completed on the replacement microscope: 8.4% of tolerance (illustrative figure).
  • All equipment changes in the past 12 months reviewed for the same gap. Two more found; both now validated.

Effectiveness check: The next three equipment changes will be checked at the follow-up audit.

Closure tracker

IDSeverityResponseVerificationStatus
F-01MinorAcceptedDocument reviewClosed
F-02MajorAccepted on second responseFollow-up auditPending verification
F-03MinorAcceptedDocument reviewClosed
F-04MinorAcceptedDocument reviewClosed
F-05MinorAwaiting responseDocument reviewOpen
F-06MajorAcceptedFollow-up auditPending verification
F-07MajorContainment confirmed; root cause dueFollow-up auditOpen

The client sees this tracker for every audit. The client, not us, accepts each closure.